Dr. George Stanley School

585 Cranston Drive SE, Calgary AB T3M 0J4

Community | Cranston
Capacity | 900
Anticipated Opening Date | Jan. 2017
Grades | 4-8 (year 1); 4-9 (Year 2) 

Registration
School Website
Career Opportunities

​Dr. George Stanley School Opening

This school is now open.

Construction Status

The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.
 
January 2017
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Foundations 100%
Steel Fabrication and Erection 100%
Roofing and Membranes 100%
Building Envelope 100%
Interior Finishes 100%
 
 
December 2016
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Foundations 100%
Steel Fabrication and Erection 100%
Roofing and Membranes 100%
Building Envelope 100%
Interior Finishes 100%
Note: The construction is complete, and occupancy has been granted.  
 
November 2016
 
The building envelope complete. Roofing installation is complete. Insulation and vapour barrier on exterior walls complete. Mechanical and electrical rough-ins and duct work is complete. Window frames and glazing installation complete. Internal partitions and drywall complete. Painting and ceiling tile installation is complete. While the work has been progressing well, this project has experienced significant weather related impacts.
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Foundations 100%
Steel Fabrication and Erection 100%
Roofing and Membranes 100%
Building Envelope 95%
Interior Finishes 90%
Note: N/A  

Project Background

December 2015
  • A full Building Permit has been issued.
September 2015
  • After tender reviews and approvals by Alberta Infrastructure and the Board, a Letter of Award was issued to Delnor Construction Ltd. Mobilization and construction has commenced.
 
May 2015 
  •  Design and tender documents prepared for tender
 February 2015
  • Open House held  at the Education Centre for stakeholders to view design plans.

  • The Province advised the CBE that the schools that were announced in October 2014 as starter schools would be funded for full construction.
 

October 2014

 

September 2014

  • The Calgary Board of Education received approval from the Province of Alberta to build a starter school for the community of Cranston.
 

2014

Design and Construction

  • Riddell Kurczaba Architects
  • Delnor Construction Ltd.

 
 

 Contact Us

 
 

 Meet Your Principal | Patty Numan

 
 

 Maps

 

​Attendance Area

 

Walk Zone

 

Click the map below to view the walk zone for your school. To find out on how walk zones are determined and answers to frequently asked questions visit our school walk zone page.

 

 

 Announcements

 
 

 Supporting Documents

 
​May 30, 2016 Questions & Answers for Parent Night
​May 30, 2016 2016-2017 Dr. George Stanley School Traditional School Calendar
​Apr. 28, 2016 School Bell Times Letter
​Apr. 11, 2016 ​Questions and Answers
​Jan. 2016 Community Engagement Plan
​Dec. 15, 2015 Parent Feedback
​Oct. 20, 2016 Site Map
 