Building & Modernizing Schools Jack James High School

Jack James High School

5105 8 Ave. S.E. Calgary, AB, T3K 2S3
Anticipated Completion Day: Sept. 2024
Move of Louise Dean Centre​

Project Description

On Nov. 29, 2022, the Board of Trustees approved the closure of Louise Dean Centre effective June 28, 2024 for the purpose of relocation to Jack James High School.

To support this move, modifications will be made to Jack James High School to create the space required for Louise Dean Centre students. This includes dedicated learning spaces for Louise Dean programming, a new child-minding space to accommodate their children, and office space for partner support.

The estimated cost for this project is approximately $7​ million. On April 12, 2023, the provincial government provided $3 million in support of the renovation and transition.

Modernization Status

The construction status is updated using the Construction Projects Status Report that is presented quarterly to the Board of Trustees.

January 2024

​Design and specifications
100%
​Construction Award (Phase 1)
​100%​​
​Construction Progress (Phase 1)
100%
​Construction Award (Phase 2)
​100%
​Constructio​n Progress (Phase 2)
   ​18%
​​Note: Project managed by Calgary Board of Education Phase 1 completed on August 25, 2023. Phase 2 tender awarded on August 31, 2023. Phase 2 construction started on September 1, 2023
​​


 