​High School Grades 10-12 | Modernization

Expected Completion Date | Fall 2018

Modernization Update | Sept. 2017

With our school year well underway, I am updating you on the modernization work that is continuing at James Fowler. 

The construction advanced during the summer as the construction team, Clark Builders, had the opportunity to work in an empty school. Work in the CTS area of the school included new HVAC, sprinklers, walls and flooring. A new floor was installed in the Student Centre. The abatement of asbestos was completed in the Learning Commons which also resulted in all of the walls being painted. New LED lighting was installed in the main area of the Learning Commons and the conference room had new ceilings and LED lighting installed.The team will continue with the installation of additional new LED lighting in the Learning Commons and the existing bay windows will be replaced by new patio-style windows that will provide students access to the new landscaped instructional use courtyard.

We also had our security and fire alarm system upgraded as well as our wireless system. Work on the full size elevator project was started with the completion of the elevator shaft. The installation of the elevator will be completed the following summer.

During the next few months the construction team will complete the renovation of the CTS area where the shops are located, including the installation of equipment and the construction of new washrooms. Automotives, Autobody, Fabrication, Building Trades, Networking and Communication Technology will be ready for students at the start of the second semester in January.

Work will also proceed in the Arts-Centred Learning room with the installation of a new “Lula lift” that will provide barrier-free access to the dance and music room in the lower level.

During the second half of the year, construction will begin in the areas of Robotics, Domestic Foods, Fashion, PLP, Arts-Centred Learning and Cosmetology. 

Further updates will be provided as the modernization progresses. Please contact me if you have any questions or concerns.

Sincerely,

Keith Johnson, Principal
James Fowler High School

Construction Status

The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.

Oct. 2017
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Tender to subtrades 100%
Award to subtrades 100%
Construction Progress 45%
​Note: Phased construction proceeding as planned.
 
Sept. 2017
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Tender to subtrades 100%
Award to subtrades 100%
Construction Progress 30%
​Note: Phased construction proceeding as planned.
 

Project Background

  • Proposals for Construction Management Services were issued in June and recommendations were made to Alberta Infrastructure in July for appointments to be made. Awaiting Alberta Infrastructure approval of Construction Management, commencement to proceed immediately upon award in September. (Sept. 2016)
  • 90% Design drawings are currently being reviewed and finalized. (June 14, 2016)
  • A design Development Report has been prepared. Working drawings are being prepared for a Summer tender. (Apr. 12, 2016)
  • A design Development Report is being prepared. (Mar. 8, 2016)
  • Taff Architecture has been appointed to lead the Design Team. Steering Committee Meetings have commenced. (Dec. 8, 2015)
  • An RFP for Design Services and Design Consultants has been prepared and is to be issued to the marketplace. Appointments are expected to be made in September. (Sept. 15, 2015)
  • Onsite inspections and program assessments are being undertaken with the Province to determine an agreed scope of work.
  • The CBE will oversee the modernization

School Community

James Fowler High School is located in the northwest community of Highland Park.

The school serves the communities of Cambrian Heights, Castleridge, Coral Springs, Falconridge, Greenview, Highland Park, Highwood, Martindale, Monterey Park, North Haven, Pineridge, Queen's Park Village, Rundle, Taradale, Temple, Thorncliffe, Tuxedo Park, Whitehorn, and Winston Heights/Mount View.

School Facility

The school was built in 1962 and is situated on 13.34 acres. The school has 78 classrooms, a library, beauty culture room, music room, art room, drama room, theater, three gymnasiums, six science labs, a staff planning room, business education labs and 12 Career and Technology technical shops.

Project Background

  • On March 31, 2015 - the Province committed to fully fund the modernization.
  • On Oct. 8, 2014 – the Province committed to the immediate planning and development of design scope of the high school modernization.
  • 2010 – James Fowler High School was identified as a priority for modernization on the CBE Three-Year Capital Plan.

 Working with Community

  • We will work with the James Fowler High School community including parents, teachers and staff.
  • We are committed to providing regular updates on this webpage.
  • You can provide feedback through the Your Voice Feedback Form
 
 

 Contact Us

 
 

 Construction Photos

 

​Construction photos are updated using the Construction Project Status Report that is presented monthly to the Board of Trustees.

 

 Announcements

 

​Sept. 2017 ​Modernization Update
​June 2017 Questions & Answers
​May 2017 Modernization Update
​May 2017 Questions & Answers
​Apr. 18, 2017 Modernization Update
 

 

 

 Provide Input

 

If you have any feedback that you would like to share with us, please fill out our online form.

 

 

Dialogue Feedback Form​​
Last modified: 10/23/2017 2:14 PM