Building & Modernizing Schools : James Fowler High School

Building & Modernizing Schools

James Fowler High School

​High School Grades 10-12 | Modernization

Expected Completion Date | Fall 2018

Modernization Update | May 2017

James Fowler High School Modernization Update | May 2017

Construction Status

The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.

June 2017
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Tender to subtrades 100%
Award to subtrades 100%
Construction Progress 10%
​Note: Planning of work sequencing continues to align with operational constraints.
 
May 2017
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Tender to subtrades 100%
Award to subtrades 100%
Construction Progress 5%
​Note: Planning of work sequencing commenced is underway.
 

Project Background

  • Proposals for Construction Management Services were issued in June and recommendations were made to Alberta Infrastructure in July for appointments to be made. Awaiting Alberta Infrastructure approval of Construction Management, commencement to proceed immediately upon award in September. (Sept. 2016)
  • 90% Design drawings are currently being reviewed and finalized. (June 14, 2016)
  • A design Development Report has been prepared. Working drawings are being prepared for a Summer tender. (Apr. 12, 2016)
  • A design Development Report is being prepared. (Mar. 8, 2016)
  • Taff Architecture has been appointed to lead the Design Team. Steering Committee Meetings have commenced. (Dec. 8, 2015)
  • An RFP for Design Services and Design Consultants has been prepared and is to be issued to the marketplace. Appointments are expected to be made in September. (Sept. 15, 2015)
  • Onsite inspections and program assessments are being undertaken with the Province to determine an agreed scope of work.
  • The CBE will oversee the modernization

School Community

James Fowler High School is located in the northwest community of Highland Park.

The school serves the communities of Cambrian Heights, Castleridge, Coral Springs, Falconridge, Greenview, Highland Park, Highwood, Martindale, Monterey Park, North Haven, Pineridge, Queen's Park Village, Rundle, Taradale, Temple, Thorncliffe, Tuxedo Park, Whitehorn, and Winston Heights/Mount View.

School Facility

The school was built in 1962 and is situated on 13.34 acres. The school has 78 classrooms, a library, beauty culture room, music room, art room, drama room, theater, three gymnasiums, six science labs, a staff planning room, business education labs and 12 Career and Technology technical shops.

Project Background

  • On March 31, 2015 - the Province committed to fully fund the modernization.
  • On Oct. 8, 2014 – the Province committed to the immediate planning and development of design scope of the high school modernization.
  • 2010 – James Fowler High School was identified as a priority for modernization on the CBE Three-Year Capital Plan.

 Working with Community

  • We will work with the James Fowler High School community including parents, teachers and staff.
  • We are committed to providing regular updates on this webpage.
  • You can provide feedback through the Your Voice Feedback Form
 
 

 Contact Us

 
 

 Announcements

 

​June 2017 Questions & Answers
​May 2017 Modernization Update
​May 2017 Questions & Answers
​Apr. 18, 2017 Modernization Update
 

 

 