Skip Ribbon Commands
Skip to main content
Navigate Up
Sign In
Banner | Lord Beaverbrook High School
Building & Modernizing Schools : Lord Beaverbrook High School
Skip Navigation LinksCBE Home Schools Building & Modernizing Schools Lord Beaverbrook High School

Building & Modernizing Schools

Lord Beaverbrook High School

​High School Grades 10-12 | Modernization

Expected Completion Date | Fall 2018

Modernization Update

Aug. 2017

Over the summer there has been a significant amount of construction activity both in and around Lord Beaverbrook High School. We are very excited about the progress being made and the changes we see happening to our school facilities. Here is an update:

Main floor:

  1. Complete - Construction and relocation of the Business Studies classroom (NW corner of the school). Update to the instructional space for the adjoining Leadership program.
  2. Complete - Construction and relocation of a new classroom space for the Adapted Learning Program. The program will be relocated to the SW corner of the main floor.
  3. In progress – Construction of the Culinary-Professional Cooking Lab and adjoining classroom space.
  4. In progress – Construction of the Cosmetology lab.
Second floor:
  1. Complete - Construction and relocation of the Sports Medicine classroom (across the hallway into a larger instructional space.)
  2. In progress - Construction of the Auto Body shop.
  3. In progress – Construction of the Fabrication/Welding shop.
  4. In progress – Construction of Building Construction and Woodworking shops.
  5. In progress – Construction of a new computer lab (formerly Sports Medicine classroom.)

Classroom instruction will continue in all programs. In Fabrication/Welding, teachers have adjusted the order of units of instruction. Students will begin their course completing theory related activities and then move into the new shop for practical application. The Culinary-Professional Cooking program will relocate to Dr. Norman Bethune School (across the school field from Lord Beaverbrook), and access the fully equipped Foods lab for instruction. The Auto Body program will continue to operate and share space with the Automotive program.

Inside the school, students can anticipate safety barriers built around the construction areas. These barriers will be found mostly in hallways. Students are asked to be considerate of the workspace, and be considerate for each other as they move between classrooms and around the school.
Loss of food service in Cafeteria for duration of construction.

There will be no food service available to students, staff or community for the duration of construction. Until completion, (anticipated November 2017) students should make alternate arrangements for lunch.

The cafeteria space will be available and accessible (as normal) during the school day for the duration of construction. Students can continue to access this space before school, on spare, at lunch, and after school.
North side of our school is out of bounds to students.

This includes the street that runs along the north side of our school, ending in Ashley Crescent. Before, during and after school hours, students should not be in this area for safety reasons. Cooperation of everyone is appreciated.

You can keep up-to-date on the progress of the modernization through this project page on the CBE website.

Further updates will be provided as needed.

Jim Simpson, Principal
Lord Beaverbrook

Construction Status

The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.

​​
Oct. 2017
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Tender to subtrades 100%
Award to subtrades 100%
Construction Progress 50%
​Note: Phased construction proceeding as planned.
   
 
​​
Sept. 2017
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Tender to subtrades 100%
Award to subtrades 100%
Construction Progress 40%
​Note: Phased construction proceeding as planned.  
 

Project Background

Sept. 2016

  • Proposals for Construction Management Services were issued in June and recommendations were made to Alberta Infrastructure in July for appointments to be made.

June 2016

  • 90% Design drawings are currently being reviewed and finalized.

Apr. 2016

  • A design Development Report has been prepared. Working drawings are being prepared for a Summer tender.

March 2016

  • A design Development Report is being prepared.

February 2016

  • Design Team has commenced detailed assessment of the school and has developed conceptual schematic layouts of the required programme spaces.

January 2016

  • Steering Committee Meetings have commenced.

December 2015 

  • Riddell Kurczaba Architects have been appointed to lead the Design Team. Steering Committee Meetings have been set-up.

September 2015

  • An RFP for Design Services and Design Consultants has been prepared and is to be issued to the marketplace. Appointments are expected to be made in September.

 

  • The CBE will oversee the modernization
  • Onsite inspections and program assessements are being undertaken with the Province to determine an agreed scope of work, prior to the appointment of Consultants.

School Community

Lord Beaverbrook High School is located in the southeast community of Acadia.

The school serves the communities of Acadia, Copperfield, Cranston, Deer Ridge, Deer Run, Diamond Cove, Douglasdale/Glen, Fairview, Maple Ridge, McKenzie Lake, McKenzie Towne, New Brighton, Parkland, Queensland, and Willow Park.

School Facility

Lord Beaverbrook High School opened in 1968.

Project Background

  • On March 31, 2015 - the Province committed to fully funding the modernization.
  • On Oct. 8, 2014 – the Province committed to the immediate planning and development of design scope of the high school modernization.
  • 2010 – Lord Beaverbrook High School was identified as a priority for modernization on the CBE Three-Year Capital Plan.

Working with Community

  • We will work with the Lord Beaverbrook High School community including parents, students, teachers and staff.
  • We are committed to providing regular updates on this webpage.
  • You can provide feedback by clicking on the Your Voice Feedback Form
 
 

 Contact Us

 
 

 Construction Photos

 

​Construction photos are updated using the Construction Project Status Report that is presented monthly to the Board of Trustees.

 

 Announcements

 
​Aug. 2017 Modernization Update
​May 2017 ​Modernization Update
​Nov. 2016 ​Modernization Update
 
 

 Provide Input

 

If you have any feedback that you would like to share with us, please fill out our online form.

 

 

Dialogue Feedback Form​​
Last modified: 10/23/2017 2:15 PM
Website feedback: Webmaster
^