Cranston Second Elementary School
Building & Modernizing Schools : Cranston Second Elementary School
Skip Navigation LinksCBE Home Schools Building & Modernizing Schools Cranston Second Elementary School

Building & Modernizing Schools

Cranston Second Elementary School

66 Cranford Drive SE

Anticipated Opening Date | September 2020
Grades | K-4

New School Naming Survey

The Calgary Board of Education is building a new elementary school for the community of Cranston. A school naming committee has been set up to recommend a name to the Board of Trustees. The committee has shortlisted three possible names and wants your input before making a recommendation to the Board.  

Please complete the naming survey online by 4 p.m., October 4, 2019. A decision on the new school's name will be made in the fall of 2019. Thank you for participating! 

New Cranston Elementary School Online Survey 

The Calgary Board of Education is scheduled to open a second elementary school for the community of Cranston during the 2020-21 school year. The opening of this school will have an impact on grade configurations and attendance areas of the existing schools in the communities.

An open house was held Sept. 18, 2019 for the community to learn about the changes and provide feedback on options prior to finalizing the attendance area for the new school. The information presented at the open house can be found in Supporting Documents.

Families are encouraged to share their perspectives on the options by completing an online survey. The survey will remain open until midnight, Oct. 1

 

Construction Status

The construction status is updated using the Construction Projects Status Report.

May 2019

Design and specifications​ ​100%
​Construction Award ​100%
​Construction Progress
​1%
Note: Project managed by Alberta Infrastructure. Contractor mobilized to site March 2019. Erosion and sedimentation control and site preparation underway.

Feb. 2019

Design and specifications​ ​100%
​Construction Award ​100%
​Construction Progress
​0%
Note: Project managed by Alberta Infrastructure. Contractor anticipated to mobilize to site in February 2019. ​​
 