Mahogany Elementary School
210 Mahogany Way SE (subject to change)
Anticipated Opening Date: Summer 2022
Grades | K-4
Capacity | 600
Construction Status
The construction status is updated using the Construction Projects Status Report.
Dec. 2020
Design and Specifications
|
100%
|
Construction Award | 100% |
Construction Progress | 1% |
Note: Project managed by Alberta Infrastructure. Construction team has mobilized to site; excavation underway
|
|