116 Brightondale Park SE, Calgary AB T2Z 0V1
Community | New Brighton/Copperfield
Capacity | 900 students
Anticipated Opening Date | March 2017
Grades | 5-8 (year 1); 5-9 (year 2)
RegistrationSchool WebsiteCareer Opportunities Construction Status
The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.
April 2017
| Design and Specifications |
100% |
| City Permits |
100% |
| Construction Award |
100% |
| Foundations |
100% |
| Steel Fabrication and Erection |
100% |
| Roofing and Membranes |
100% |
| Building Envelope |
100% |
| Interior Finishes |
100% |
March 2017
| Design and Specifications |
100% |
| City Permits |
100% |
| Construction Award |
100% |
| Foundations |
100% |
| Steel Fabrication and Erection |
100% |
| Roofing and Membranes |
100% |
| Building Envelope |
100% |
| Interior Finishes |
95% |
Project Background
Summer 2015
- After tender approvals by Alberta Infrastructure and the Board, a Letter of Award was issued to Maple Reinders. Mobilization and construction has commenced. A partial Building permit has been issued.
June 2015
May 2015
March 2015
- The development permit application was approved by the City.
February 2014
- The Calgary Board of Education received approval from the Province of Alberta to build a new school in the community of New Brighton.
2010
- New Brighton Middle School was identified as a priority on the CBE School Three-Year Capital Plan.
Design and Construction
- Bridging Consultant - Group 2 Architecture
- Construction - Maple Reinders